After Plans are Approved - Building Permit is Issued - Construction Begins
- Keep 1 set of approved plans on-site during construction.
-
Any change orders must be approved by the Tippecanoe County Health
Department and or Building Code Official having Jurisdiction.
Pre-Operational
Call the Tippecanoe County Health Department after equipment is
installed to request a pre-operational inspection. A punch list of items
will be provided at this time that must be completed before an
operational permit will be issued.*
Submit complete operational
permit application with payment of all appropriate fees making checks
payable to the Tippecanoe County Health Department.*
- Schedule opening Inspection by Tippecanoe County Health Department.*
- Schedule final Inspection by Building Code Officials having Jurisdiction.
Certificate of Occupancy Signed - Operational Permit Issued - Establishment Opens
*Failure to complete the application packet, items on pre-operational
punch list, and permit application with payment of all appropriate fees
will delay the issuance of an operational permit by the Tippecanoe
County Health Department and the establishment's opening date.